Electrical installation in a new-build villa: stages, coordination and sign-off

Writer: Aymeric Brun
Aymeric Brun
3 days ago
3 min read

In short: the electrical installation of a new villa is decided long before the first cable goes in. It starts with the architect's drawings and the power demand calculation, continues with conduits and boxes during the structure and walls, then cabling and consumer units, and ends with testing, the installation certificate and connection by the distribution company. The expensive mistakes are almost always made at the start, when they are still cheap to fix.

Stage 1: design and power demand

Working from the architectural drawings, we define where every light point, socket, switch and appliance goes: air conditioning, heat pump, pool, irrigation, outdoor lighting, home automation. From there we calculate the power the villa needs and size the supply, the meter tails and the consumer units.

In a high-end villa on the Costa del Sol, the installation usually falls under the "high electrification" category of the Spanish low-voltage regulations (REBT), because of floor area and equipment. It is worth getting right: an underestimated power demand means tripping breakers or having to upgrade the supply later.

Stage 2: first fix during construction

While the structure and walls go up, conduits, junction boxes and back boxes are installed. This is the stage where the electrician has to work as part of the team with the other trades: builders, plumbers, air conditioning installers and joiners.

This is also when you plan the routes that are impossible to add later without building work: the cable to the front door for a motorised lock, the bus conduits for home automation, garden and pool light points, the data network, and boxes for motorised blinds and awnings.

Stage 3: cabling, consumer units and second fix

Once partitions are closed and before the finishes, the cabling is pulled through and the consumer units are built. A good villa consumer unit is tidy, with labelled circuits and RCDs spread out so that one fault does not leave the whole house without power.

Switches, sockets and light fittings go in at the end, once painting and joinery are finished, to avoid damage and rework.

Stage 4: testing, certificate and connection

Before handover, measurements and checks are carried out: insulation, continuity, earthing and correct operation of the protective devices. Once the installation is complete, the licensed installer issues the Electrical Installation Certificate (known in Spain as the boletín), which is registered with the Junta de Andalucía and is needed to sign the permanent supply contract with the distribution company. We explain it on our electrical certificate page.

Coordination with the architect and the builder

Most problems with electrical installations in new builds are not technical but about coordination: a layout change that never reaches the electrician, a kitchen unit that covers a box, joinery fitted before a cable has gone through. That is why we work from the same drawings as the rest of the team, every change is quoted before it is carried out, and the final documentation reflects what was actually installed.

What to decide early

  • Home automation: even if KNX is not installed from day one, laying the bus conduit costs little and avoids building work later.

  • Outdoor and pool lighting, which needs dedicated circuits and weatherproof boxes.

  • Access control: intercom, smart lock and gates.

  • The data network and wifi coverage across the whole plot.

  • Where the consumer units go: accessible but discreet.

How we work at Sostera

We are a licensed electrical installation company working with architects, builders and owners between Málaga and Estepona, from the drawings to the signed-off villa. See the full service on our new-build villas page and some of our work in projects.

Frequently asked questions

When should the electrician get involved in a new build?

Ideally at design stage, working from the architect's drawings, and then during the structure and walls for the first fix.

Who issues the electrical certificate?

The licensed installer who carried out the installation, once it has been completed and tested.

Can home automation be added later?

Yes, but it is much simpler and cheaper if the bus conduit was laid during construction.

What documentation is handed over at the end?

The installation certificate, the consumer unit diagrams and the circuit schedule.

 
 
 